Project Gries: publication of proposals

12.12.2011Bruck an der Grossglocknerstrasse

The project team supports interested parties in the inspection of comprehensive documents accompanying the Environmental Impact Assessment.

17 files of project documentation
The procedural documents for the Salzach power plant in Gries are available for public inspection. Project manager Hannes Badura and his team were on hand to provide assistance in ensuring that, from a total of 17 folders, all interested parties were also able to locate the documents that were personally relevant to them.

30 information talks with 50 interested parties
Over the course of two afternoons, some 30 information talks were held with around 50 people. “The one-on-one talks gave us the possibility to respond precisely to the areas of interest of the party concerned and thus offer a great deal of assurance,” says Badura.